Office for National Statistics, NewportThe Office for National Statistics (ONS) have sites across the UK and Bbi have undertaken many projects across all sites. The Newport project was a two million pound contract to upgrade two floors of one of the buildings on the Newport Site.
This project involved the complete strip out (to core) of two large floors, each floor comprising four 'wings'. Internal construction comprised:
Variations to the project included the design and installation of a new Air Handling Unit.
The project was split into two phases - one phase for each floor with each phase taking twenty weeks. Asbestos removal and demolitions took a fortnight within each phase with a continual sequence of works carrying on from that. Mechanical and Electrical installations were completed on schedule, despite the Versatemp Units being delayed due to the Tsunami of Boxing Day 2004. Internal construction elements were based on the ONS Style Guide (an organisational standards document) that BBI had designed on behalf of the ONS previously.
|
|
|||||||||||||||||||||||||||||||||||||